user requirement specifications Archives - European Industrial Pharmacists Group (EIPG)

The EU Parliament voted its position on the Unitary SPC


by Giuliana Miglierini The intersecting pathways of revision of the pharmaceutical and intellectual property legislations recently marked the adoption of the EU Parliament’s position on the new unitary Supplementary Protection Certificate (SPC) system, parallel to the recast of the current Read more

Reform of pharma legislation: the debate on regulatory data protection


by Giuliana Miglierini As the definition of the final contents of many new pieces of the overall revision of the pharmaceutical legislation is approaching, many voices commented the possible impact the new scheme for regulatory data protection (RDP) may have Read more

Environmental sustainability: the EIPG perspective


Piero Iamartino Although the impact of medicines on the environment has been highlighted since the 70s of the last century with the emergence of the first reports of pollution in surface waters, it is only since the beginning of the Read more

ECA’s guide to compliant equipment design

, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

By Giuliana Miglierini

The legislative evolution of the last decades emphasised requirements for equipment used in pharmaceutical productions. This is even more true with the entry into force of the new Annex 1 to the GMPs, characterised by many new requirements impacting on different manufacturing processes (i.e. production of water for injection, sterilisation, Form-Fill-Seal and Blow-Fill-Seal technologies, single use systems, lyophilisation, etc.).

Each pharmaceutical process requires the careful design of the needed equipment in order to provide the expected efficiency and performance. Furthermore, some equipment may be used for different industrial applications (e.g. pharmaceutical, cosmetic or food), thus needing a fine tuning to reflect relevant requirements. In pharmaceutical manufacturing, a further step of complexity may be represented by the need to handle highly potent active pharmaceutical ingredients, requiring isolators to segregate production, etc.

To facilitate the correct design of equipment compliant to GMPs, a new guidance document has been published by the ECA Foundation. The document was initially drafted in German by a task force of experts in pharmaceutical technology and engineering and published by Concept Heidelberg, and it has now been translated in English

Elements relevant to reach compliance

The first part of the document discusses general requirements that should always be part of the design of GMP-compliant equipment. Four different points of attention are listed: the equipment must not adversely affect the product quality, it must be easy to clean, it must comply with applicable technical rules, and it must be fit for its intended use.

As for the first point, “The question is rather what is tolerable without adversely affecting the product quality”, states the guidance. Avoidance of contamination and cross-contamination are the main goals of cleaning activities, both for sterile and non-sterile medicinal products. There are several issues to be taken in mind from this perspective, including the presence of endotoxins, sealing points, the efficiency of cleaning-in-place (CIP) processes, or the presence of unreachable dead leg areas. According to the guidance, the 3D/6D rule for the prevention of dead legs in water systems often used for specification would not always be correctly applied, due to some confusion in terminology. Official GMPs are also deemed “very vague”, as they are not drafted by engineers and apply to an extremely wide range of different equipment and processes. “Consequently, the question is, which technical rules have to be followed or where the actual state of the art can be looked up”, says the document. Many different references are possible, from pharmacopeia monographs and regulatory guidelines, to ISO standards, and other documents published by international professional bodies.

Qualification and calibration of equipment should always be targeted to the specific product, as it is an essential in proving compliance to the intended use. Regulatory compliance of submitted documentation is not less important, and it greatly impacts on change control and implementation of new productive technologies.

Risk analysis (RA) is the tool introduced in 2005 by ICH Q9 to evaluate all items which may impact on the design of productive processes and related equipment. There is no standard methodology to run risk analysis, the choice depends on the process/product under assessment. According to the guidance, RA can be performed both from the perspective of the product and the equipment, the latter being also considered a GMP risk analysis.

Design and choice of materials

Materials (and coating materials where relevant) used to build pharmaceutical equipment should be completely inert. Pharmaceutical equipment must comply with the EC Directive on Machinery 2006/42/EC and DIN EN ISO 14159. The ECA guidance discusses material selection (plastics or stainless steel); hygienic system design is also addressed by many different guidelines, e.g. those published by the European Hygienic Engineering and Design Group (EHEDG). An important item to consider is service life considerations for the materials used (EHEDG Document 32), as well as their chemical-physical characteristics and materials pairing.

Particularly critical are process contact surfaces, as they may impact product quality. Establishment of specific requirements is thus needed. The guidance focuses its attention on austenitic stainless steels (i.e. CrNiMo steels 1.4404 and 1.4435). The main elements to be assessed are the risk of corrosion, the risk of contamination of the product or process medium and the cleanability of the metallic surface. Topography, morphology and energy level are the main characteristics to be used to describe surfaces, addressing respectively the geometric shape, chemical composition and energy required per unit area to increase the size of the surface. The guidance provides a detailed discussion of all different aspects of surface treatment methods, and the hygienic design of open and closed equipment. Other sections discuss the optimal design of pipework and fittings, connections, welding and seam control. Detailed information is also provided on equipment of electrical engineering, measurement and control technology, as well as the process control technology (PCT) measurement and control functions.

A highly critical area within a pharmaceutical facility are cleanrooms, for which the design of the equipment and the choice of materials is even more stringent. Elements to be considered include stability/statics as concerns dynamic loads, smoothness of the floor, tightness of external façades and of enclosing surfaces of cleanrooms. Smooth nonporous surfaces are required, together with avoidance of molecular contamination, resistance to the intended cleaning or disinfection agents and the cleaning procedure, simple and tight integration of various fittings, efficient and rapid implementation of subsequent functional and technical changes. The ECA guidance document goes deeper into relevant requirements for all elements that are part of the design of a compliant cleanroom.

Documentation and automation

User requirement specifications (URS) are the key document to demonstrate equipment is fit for the intended use, as stated by GMP Annex 15 (2015). The ECA guidance suggests translating the URS in a technical version to be submitted to the potential equipment supplier, so to ensure the design would reflect product and quality-relevant requirements, being thus GMP compliant.

The management of documentation along the design life cycle of a new piece of equipment is also taken into consideration, with the different construction phases identified according to Good engineering practices (GEP): conceptual design, basic design/engineering, and detailed design/engineering.

The extensive use of data to monitor and document pharmaceutical manufacturing process represents another area of great attention. Requirements relevant to the design of validated computerised systems, data protection and data integrity must be kept in mind. ECA’s experts highlight the need to carefully delimitate areas subject to validation and their extention, particularly with reference to automated systems. Differences between qualification and validation of automated systems are also addressed, including equipment that might either be defined as “computerised” or “automated” system. Regulatory reference for validation is GAMP 5, while qualification refers to Annex 15.


FAT and SAT, a critical step for the introduction of new equipment

, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

by Giuliana Miglierini

There are two key moments to be faced to introduce a new piece of equipment in a pharmaceutical plant: a factory acceptance testing (FAT), usually performed by its manufacturer to verify the new equipment meets its intended purpose, prior to approve it for delivery and once arrived at its final destination and installed, a site acceptance testing (SAT) run by the purchasing company and is part of the commissioning activity.

According to an article published in Outsourced Pharma, the commissioning of a new piece of equipment poses many challenges, and criticalities needs to be considered both from the business and regulatory point of view. Pharmaceutical plants are very complex and often customised upon the specific business needs, and the delivery of a new equipment requires the interaction of many different parties, both internal and external to the purchasing company. FAT, SAT and commissioning activities require a careful planning and detailed responsibilities for all participating parties to be included within the Commissioning and Qualification Plan (CQV plan). A possible responsibility matrix is suggested by the authors to provide clarity and ensures ownership of activities.

FAT, assessing the equipment at the manufacturer site

FAT and SAT testing involve the visual inspection of the equipment and the verification of its static and/or dynamic functioning, in order to assess the actual correspondence to the user requirement specifications (URS). While FATs are usually based on simulations of the equipment’s operating environment, SAT testing occurs at the final site after installation, thus it reflects the real operating conditions and environment in order to support qualification.

There are many different elements to be considered during FAT testing, including for example verification of the existing site drainage, piping, or room dimensions, or the position of the handle for accessibility, as well as software design specification, interface, and device integration.

The FAT exercise is always highly recommended, as it is essential to solve in advance (before shipment to the final destination) any error or malfunctioning of the equipment, that otherwise might occur at the purchasing company’s site. This results in the optimisation of the delivery and commissioning process, with important savings in terms of both time and costs for the purchasing company. To ensure for the transparency of FAT testing, the entire procedure (that requires usually 1-3 days, depending on the complexity of the equipment to be verified) is usually performed in the presence of a third party inspector and customer representative.

A comprehensive set of documentation should be always available to support FAT, including URS, drawings, checklists and procedures, calibrations and certifications, data sheets, references, etc. Raw data acquired during FAT are transmitted to the customer for analysis and validation. FAT should take into consideration all aspects relevant to the evaluation of the safety and functionality of the equipment and its compliance to URS, GMPs and data integrity. To this regard, it is also important for the engineering team called to run the new equipment at its final location to learn and share knowledge with the manufacturer along the entire commissioning process, so to increase the first-hand direct experience. According to the article, this is also critical to authorise the shipment of the equipment to the final destination, a step that should always be performed by an authorised, trained, and approved subject matter expert.

 SAT acceptance testing

All criticalities emerged during the FAT exercise are then checked again at the final site, after installation and verification; additional test cases may also be added to the SAT protocol to check for potential failure modes. SAT testing is performed once all connections between the new equipment and other machines/softwares are in place, under the real operating parameters, and may be witnessed by a representative of the equipment’s manufacturer.

Results from SATs may thus differ from those obtained from the FAT previously run by the manufacturer. From the regulatory point of view, SAT testing is a key element to demonstrate the compliance of the equipment to GMP requirements and to support the overall quality and safety of pharmaceutical productions. In this case too, many are the possible elements to be inspected and verified, including interlocks, ventilation, internal box pressure, electrical/hydraulic connections and safety systems, visual checks of components, training of the operators, etc.

A plan for each testing phase

FAT planning begins at the very moment of the purchasing company placing the order for the new equipment, and it has to reflect all URS to be checked for acceptability of the manufactured apparatus. This step in the design is critical and calls for a strict and positive communication between the manufacturer and its customers, a key point to take into consideration all elements that should enter the project.

All identified items and procedures to be challenged during FAT and SAT testing are usually addressed within the CQV plan, that connects the design phase to user requirements specifications and the other elements impacting the commissioning and qualification processes (i.e. system impact assessment, design specification, functional risk assessment, hardware / software specifications, Installation / Operational / Performance Qualification), including deviations and change management. The plan specific to SAT testing should include the scope, test specifications and logs, a test summary, the Commissioning report and the final Certificate of Acceptance.

Transparency and a robust statistical approach should represent main targets along the entire commissioning and validation procedure, that may be run with the assistance of external consultants. All activities that shall enter the regulatory dossiers should always be justified and documented, also under the perspective of data integrity. The Outsourced Pharma’s article also suggests paying a particular attention to controls on data provided by the manufacturer in the case a risk-based leveraging is applied.